High Tension Line Setback in Nepal & Building ROW Calculator
Check mandatory NEA High Tension line clearances (11kV, 33kV, 66kV, 132kV, 220kV, 400kV Right-of-Way), road centerline distance (ROW + Front Setback), and 1.5 m (5 ft) neighbor window setback before applying for municipal Naksa Pas.
Building Setback, Road ROW & Ground Coverage Calculator
4.5 m (14.8 ft)
3m ROW + 1.5m Setback1.5 m (4.9 ft)
Required when placing windows70%
Standard residential limit958 sq.ft
Remaining stays open setbackHigh Tension Line Setback Distance in Nepal (NEA & Electricity Rules 2050)
| Voltage Level | Each Side of Centerline | Total Corridor Width | Building Rule / Notes |
|---|---|---|---|
| 11 kV (Distribution Line) | 1.25 – 2.0 m | 2.5 – 4.0 m | Minimum horizontal/vertical clearance from building balconies/windows |
| 33 kV (Sub-Transmission) | 2.0 – 3.0 m | 4.0 – 6.0 m | Restricted overhead construction directly under conductor |
| 66 kV (High Tension) | 9.0 m (~29.5 ft) | 18.0 m (~59 ft) | Standard NEA Right-of-Way corridor (no permanent RCC building) |
| 132 kV (High Tension) | 9.0 m (~29.5 ft) | 18.0 m (~59 ft) | Standard NEA ROW corridor from transmission centerline |
| 220 kV (Extra High Voltage) | 15.0 m (~49.2 ft) | 30.0 m (~98 ft) | Strict transmission corridor under Electricity Rules 2050 |
| 400 kV (National Grid) | 23.0 m (~75.5 ft) | 46.0 m (~151 ft) | Maximum national grid corridor setback |
Important: Local municipal building bye-laws (such as Kathmandu Valley, Pokhara, Lalitpur, or Bharatpur) may impose additional setback requirements for commercial high-rises, rivers/kholas (typically 4m–20m depending on river class), or airport zones. Always verify your ward's E-BPS engineering checklist before construction.
NEA High Tension Line Setback & Right-of-Way (ROW) Table in Nepal
| Voltage Level | Setback from Centerline (Each Side) | Total ROW Corridor Width | Building & Bank Loan Eligibility |
|---|---|---|---|
| 230V / 400V (Low Voltage) | 1.25 m (4.1 ft) horizontal | 2.5 m | Safe outside 1.25m clearance from wire |
| 11 kV (Distribution Line) | 1.5 m – 2.0 m (~5–6.5 ft) | 3 m – 4 m | No balcony/window within 1.5m–2m |
| 33 kV (Sub-Transmission) | 3.0 m (9.84 ft) each side | 6 m (~20 ft) | No building inside 3m from centerline |
| 66 kV (High Tension) | 9.0 m (29.5 ft) each side | 18 m (~59 ft) | No house construction / bank collateral inside ROW |
| 132 kV (High Tension Grid) | 9.0 m (29.5 ft) each side | 18 m (~59 ft) | Strict No-Build Zone; 10%–20% ROW compensation only |
| 220 kV (Extra High Voltage) | 15.0 m (49.2 ft) each side | 30 m (~98 ft) | Strict No-Build & No Tall Tree Zone |
| 400 kV (National Trunk Grid) | 23.0 m (75.5 ft) each side | 46 m (~151 ft) | Strict No-Build Zone across 46m corridor |
More English Land & Utility Tools for Nepal
Number to Nepali Words
अंकबाट नेपाली अक्षरमा
Nepal Land Unit Converter
जग्गा नापजाँच क्यालकुलेटर
Malpot Tax & CGT Calculator
मालपोत रजिस्ट्रेसन र लाभकर
Kitta Kat Eligibility Checker
कित्ताकाट योग्यता परीक्षक
Government Land Valuation Rates
सरकारी जग्गा मूल्याङ्कन दर
Survey & Malpot Offices Directory
नापी र मालपोत कार्यालय निर्देशिका
Nepali Patro & BS-AD Converter
नेपाली पात्रो र BS-AD कन्भर्टर